C10 construction impacts
Monday, April 7, 2025
Construction for this project begins on Monday, April 14.
The C10 lot will undergo construction from mid-April through the end of May. Once construction is complete, four stalls will be permanently removed from the C10 lot.
Schedule
All dates below are estimates and may shift based on circumstances.
- April 14 through April 18:
15 stalls will be closed. Disability stalls will not be impacted. View image of closure details. - April 21 through May 12:
27 parking stalls will be closed, including two disability stalls and one motorcycle stall. Dial-A-Ride stop 80 will be unavailable during this time. Bike lockers 114 and 115 will be inaccessible. View image of closure details. - May 16 through May 26:
Lot will be fully closed during this period. Dial-A-Ride stop 80 and bike lockers will be unavailable. View image of closure details. -
May 26 through May 30:
Five parking stalls will be closed. View image of closure details.
About the project
This construction surrounding the C10 lot relate to a series of upgrades for the Anderson Hall Renovation project.